Friday, 29 Aug, 2025

National

Payra Thermal Power Plant resumes operation

News Desk | banglanews24.com
Update: 2023-06-25 13:34:30
Payra Thermal Power Plant resumes operation

Payra Power Plant resumed its operation on Sunday (June 25) morning, after a hiatus of 20 days due to coal shortage.

A unit capable of generating 660 MW was commenced this morning, said Shah Abdul Hasib, superintending engineer of the power plant.

The BCPCL, a joint venture of Bangladesh’s state-owned North-West Power Generation Company Limited and Chinese state-owned China National Machinery Import & Export Corporation (CMC), is the owner and operator of the 1320 MW Payra coal-fired power plant.

A ship carrying 41,327 metric tonnes of coal arrived at Payra Port yesterday – 18 days after the thermal power plant stopped electricity generation due to coal shortage.

Four more coal-carrying ships will arrive at Payra in the first week of July, according to plant officials.

The country’s largest thermal power plant, Payra, completely shut down on June 5 due to coal shortage.

Due to failure in paying the outstanding bills of $390 million, caused by dollar shortage, production of a unit of the power plant was halted on May 25 as the companies involved stopped supplying coal.

Another unit’s production continued until June 5, but that also shut down due to coal shortage – leading to weeks of nationwide load-shedding amidst the hottest summer on record.

BDST: 1334 HRS, JUNE 25, 2023
SMS

All rights reserved. Sale, redistribution or reproduction of information/photos/illustrations/video/audio contents on this website in any form without prior permission from banglanews24.com are strictly prohibited and liable to legal action.